Enbridge Energy Partners Update on Michigan Leak Clean-Up

HOUSTON, TEXAS--(Marketwire - July 27, 2010) - Enbridge Energy Partners, L.P. (NYSE:EEP) (the "Partnership") today provided an update on the progress being made in the clean-up efforts undertaken in response to the leak that occurred on Line 6B near Marshall, Michigan the morning of July 26, 2010. Community health and safety, and environmental mitigation remain top priorities.

"Crews worked through the night on containment, including the use of booms, oil skimmers and vacuum trucks. Additional crews and equipment will be onsite early Tuesday to assist with oil containment. We had approximately 50 people working through the night and we expect over 100 workers on-site during the day," said Stephen J. Wuori, Executive Vice-President, Liquids Pipelines, Enbridge Inc.

Emergency response crews are stationed along Tallmadge Creek and the Kalamazoo River to contain the oil. Crews are reclaiming the oil using a variety of different methods, including oil collection skimmers, containment and absorbent booms. A temporary dike and flume arrangement has been secured near the point of origin of the leak stopping transport into the tributary creek.

The cleanup is being conducted in compliance with all government regulations and Enbridge's own stringent standards for safety and the environment, and is being coordinated under the direction of a unified command structure at the site. Plans for remediation and reclamation of the site will be developed with the input of affected stakeholders and environmental regulators, the state and federal authorities.

"We are currently focused on bringing all available resources to bear in our efforts to safely contain the leaked oil on the Kalamazoo River. We have brought in multiple crews of trained Enbridge personnel, and continue to draw on our contractors to further augment our resources. We are members of emergency response organizations, and will continue to work with experts from those organizations to address the current situation and longer-term clean up and remediation efforts," said Mr. Wuori.

Enbridge is monitoring water quality at many points along Tallmadge Creek and Kalamazoo River and is taking measures to protect fish and wildlife from coming into contact with the spilled oil. Fish and wildlife specialists are on site to help rehabilitate affected animals.

"We'd like to acknowledge the impact this has had on the people of Marshall and the surrounding community," continued Mr. Wuori. "We extend our apologies to the people who have been affected by this. Enbridge understands that the leak has disrupted people's lives and had a major impact on the people in this community, on the environment and on wildlife. We ask you for your patience and your input as we work to clean up this leak."

The full community and environmental impacts are still being assessed. Enbridge will continue to work with the U.S. Environmental Protection Agency and the Michigan Department of Environmental Quality to complete the environmental cleanup of the site, and is working with state and local emergency response agencies to address local impacts and concerns.

"Enbridge expresses its sincere appreciation to the community of Marshall and surrounding areas emergency responders for their professional, diligent and supportive actions," said Mr. Wuori.

At this point in time, the Partnership cannot provide an estimated time for restart of the Line 6B pipeline. Enbridge appreciates the cooperation of shippers on the Enbridge system in realigning deliveries. Enbridge will work closely with all connecting carriers and refiners to minimize any service impact resulting from the leak.

The cause of the leak remains under active investigation with complete results not expected for several weeks. The section of pipeline involved will be removed and transported to a third party facility for examination and testing. Enbridge continues to work closely with federal and state agencies in the investigation, including the Pipeline and Hazardous Materials Safety Administration (PHMSA), along with state and local public safety officials.

Line 6B is a 30-inch, 190,000 bpd line transporting light synthetics, heavy and medium crude oil from Griffith, Indiana to Sarnia, Ontario. It is part of the Partnership's Lakehead System.

About Enbridge Energy Partners, L.P.

Enbridge Energy Partners, L.P. (www.enbridgepartners.com) owns and operates a diversified portfolio of crude oil and natural gas transportation systems in the United States, including the Enbridge North Dakota System. Its principal crude oil system is the largest transporter of growing oil production from western Canada. The system's deliveries to refining centers and connected carriers in the United States account for approximately 12 per cent of total U.S. oil imports; while deliveries to Ontario, Canada satisfy approximately 60 per cent of refinery demand in that region. EEP's natural gas gathering, treating, processing and transmission assets, which are principally located onshore in the active U.S. Mid-Continent and Gulf Coast area, deliver approximately 2 billion cubic feet of natural gas daily.

Enbridge Energy Management, L.L.C. (NYSE: EEQ) (www.enbridgemanagement.com) manages the business and affairs of EEP and its sole asset is an approximate 14 per cent interest in EEP. Enbridge Energy Company, Inc., an indirect wholly owned subsidiary of Enbridge Inc. of Calgary, Alberta, is the general partner and holds an approximate 27 percent interest in EEP.

This news release includes forward-looking statements and projections, which are statements that do not relate strictly to historical or current facts. These statements frequently use the following words, variations thereon or comparable terminology: "anticipate," "expect," or "will." Forward-looking statements involve risks, uncertainties and assumptions and are not guarantees of performance. Future actions, conditions or events and future results of operations may differ materially from those expressed in these forward-looking statements. Many of the factors that will determine these results are beyond Enbridge Partners' ability to control or predict. Reference should also be made to Enbridge Partners' filings with the U.S. Securities and Exchange Commission; including its Annual Report on Form 10-K for the most recently completed fiscal year, for additional factors that may affect results. These filings are available to the public over the Internet at the SEC's web site (www.sec.gov) and via the Partnership's web site.

For more information please contact:

Enbridge Energy Partners, L.P.
Gina Jordan
Media
(403) 508-6563 or Toll free: (888) 992-0997
or
Enbridge Energy Partners, L.P.
Larry Springer
(713) 821-2253 or Toll free: (877) 496-8142
usmedia@enbridge.com
or
Enbridge Energy Partners, L.P.
Douglas Montgomery
Investment Community
Toll-free: (866) EEP INFO or (866) 337-4636
eep@enbridge.com
www.enbridgeus.com